In 2016 Glomar Shipmanagment tasked us with modification of their flagship Glomar Wave with additional TTS Crane which have maximum load of 25 tonns.

 

Our task was to dismantle crane from previous vessel and install it on Glomar Wave, including necessary works, pulling cables, mounting of starter box and required power calculation.

Later together with TTS service man we had inspected working state of crane, setting of limit switches and repair of wire lenght counter. Also it was required to repair crane display E200 HMI panel.

During that time we have carried out required mainterance on board and installed additional PC for accurate map system for client use.

Also ship has now additional networks designed for divers project – CCTV distributions, additional survey screens, new client offices has been created onboard.